The link that holds the two islands together is being renewed.
The HVDC link runs from Benmore in the South Island to Haywards in the North Island, crossing Cook Strait by undersea cable. It was first commissioned in 1965. The cables in the water today were installed in 1991, and Transpower says they are due for renewal in the early 2030s.
On 18 June the Commerce Commission approved Stage 1 of Transpower's upgrade, the subject of a $1.1 billion investment proposal. Twelve days later Transpower confirmed a contract with Prysmian to make and install four new 40 km cables. Stage 1 lifts the link's capacity from 1,200 MW to 1,400 MW, and adds new cable termination stations at Oteranga Bay and ĹŚraumoa/Fighting Bay, spare cable storage, a filter bank upgrade at Benmore and an overload scheme on Pole 2.
Transpower bought its place in a global queue.
Transpower says the cables are highly specialised, in high demand worldwide and made by only a small number of suppliers. It signed a reservation with Prysmian in December 2024, before the regulator had approved anything. Speaking to Te Waihanga, the national infrastructure agency, Transpower's project lead described lead times of seven to eight years for the ships and resources, with offshore wind and interconnector projects soaking up capacity.
That early commitment looks well judged now. It also tells you the shape of the market the project team will be hiring into, because the same global boom that tied up cable factories and vessels has tied up the engineers who specify, test and commission them.
The timetable is tight at both ends.
Environmental approvals are still to come. Subject to them, Transpower plans to start site work in the summer of 2027/28, install the cables in 2031 and commission the new cables and control system in the first half of 2032. Stage 2, replacing the link's control system, goes to consultation at the end of this year.
The cable laying itself is a short window. The years either side of it are where the people are needed: design reviews, termination station construction, factory acceptance testing, protection and control integration, and the outage planning that keeps power flowing between the islands while the work is done.
HVDC experience is thin on both sides of the Tasman.
In our experience HVDC is one of the hardest skill sets to recruit in Australia and New Zealand. Each country has only a handful of links, so few engineers have worked on more than one, and many of those who have are in Europe on offshore wind and interconnector programs.
Australia is competing for the same people. Marinus Link, which reached a final investment decision in August 2025, will run HVDC across Bass Strait on cable from the same supplier, and every Australian transmission business planning long distance links is looking at the same short list. A New Zealand project with a firm date, regulatory approval and a signed supply contract is attractive to those people, but only if the offer arrives before someone else's does.
What to do about it.
Plan the owner's team now. The roles that matter most in 2030 are the ones that need hiring in 2027: HVDC protection and control engineers, subsea cable package managers, termination station project managers, consents and stakeholder leads, and commissioning managers who have energised a link before.
Use the Tasman. Engineers from Australian transmission programs, and New Zealanders working offshore who want to come home, are the obvious pool. Treat relocation and family support as part of the offer, not an afterthought.
Candidates. If you have HVDC, subsea cable or high voltage commissioning experience anywhere in the world, the early 2030s in New Zealand are worth a conversation. Few projects come with this much certainty this far out.
The cables are booked. The people are not, yet.